• Step 1:

First, make sure the sand and dust test chamber is connected to the power supply and the power switch is in the off state. Then, place the items to be tested on the test bench for detection and testing.

• Step 2:

Set the parameters of the test chamber according to the test requirements. Parameters such as temperature, humidity and sand and dust concentration of the sand and dust test chamber can be adjusted. Make sure that the parameter settings meet the required test standards.

• Step 3:

After completing the parameter settings, turn on the power switch to start the sand and dust test chamber. The test chamber will begin to generate a sand and dust environment with a certain concentration and maintain the set temperature and humidity.

Notes:

1. It should be noted that during the test, it is necessary to regularly check the sand and dust concentration in the test chamber and the status of the test items. A sand and dust concentration meter and observation window can be used to monitor changes in the sand and dust environment and ensure the normal operation of the test items.

2. When the test is completed, first turn off the power switch of the sand and dust test chamber, and then take out the test items. Clean the interior of the dust test chamber to ensure that the equipment is clean and in good condition.